| St James RC Primary School |
| |
| Location: Wigan |
| Value: £1,662,805 |
| Client: Wigan MBC |
| Duration: 28 weeks |
New Build Surestart Extension and Extensive Refurbishment of St James RC Primary School, Wigan
The works include the construction of new build surestart which comprises of a new school entrance, activity room, toilets, disabled facilities and kitchenette. The whole school is being totally refurbished, which includes, reroofing, replacement of windows and doors, external works and repointing of the external brickwork. Internally the works comprise of Strip out all existing M & E services including plant and equipment, removal of existing walls and creating new work spaces, plastering all fairfaced blockwork walls, forming new toilets and remodelling existing. Forming roof lights to allow natural light to the classrooms, replacement of internal doors and screens, installation of new suspended ceilings, replacement of soft floor finishes and redecoration to walls.
|
|
|